Hindustan Copper has recommenced operations at its Surda copper mine in Jharkhand.
The Rs 210 crore mine expansion project was stuck for nine months because of a dispute between the lead contractor and the sub-contractor. According to a source, the project work is expected to gain full swing from January 2016.
Hindustan Copper will allow an extension of time until 2018 for completion of the delayed project. The settlement involves a payment of Rs 1.60 crore by SEPC to IRCMPL.
The expansion will allow an additional life of the mine of five years and enhance Surda mine's yearly production capacity from 0.4 mln tpa to 0.9 mln tpa.