Hinduja National’s Vizag plant to go on stream by NovemberIllustrative image – not actual.

Hinduja National Power is planning to commission unit I of Visakhapatnam Power Project by November 2013.


Hinduja plans to commission 520 MW Unit I of 1,040 MW power project by November 2013. The project is located in the coast of the Bay of Bengal in village Pavalavasa, southwest of Vishakhapatnam. The company is developing the project under two phases with an estimated cost of Rs 6,202 crore. Unit II of the project is under construction and will go on stream by January 2014. Initially, the coal-fired power plant is expected to serve as a merchant power facility. But, later, the company plans to supply power generated to the state grid.
 