Illustrative image – not actual.Hindalco Industries is planning a capex of around Rs.30,000 crore ($6.7 billion) over a period of five years towards its brownfield and greenfield expansion. The expansion will be part-financed through internal accruals.
The capex will be used for capacity expansion at the Muri Alumina refinery from 1.1 lakh tpa to 4.5 lakh tpa which is slated to be commissioned in the December 2007 and the Utkal Alumina's 1.5 million tpa alumina refinery plant, which is expected to commission by March 2010.
Moreover, Aditya Aluminium, the integrated aluminium project encompassing 1-1.5 million tpa alumina refinery, 2.6 lakh tpa - 3.25 lakh tpa aluminium smelter and 750 MW captive power plant expects its smelter to be commissioned by March 2011 and the refinery by May 2011.
Also, the Mahan Aluminium project with a smelter capacity of 325,000 tpa and CPP of 750 MW is expected to be commissioned by October 2011. Lastly, the Latehar project with a smelter capacity of 325,000 tpa and CPP of 750 MW is expected to commission by March 2012.