Hindalco Q2 net rises 12 per cent to Rs.720 crIllustrative image – not actual.

Hindalco Industries' second quarter profit increased better-than-expected 12 per cent, boosted by higher metal prices and a weakening rupee that increased export earnings at India's biggest aluminium producer.

The company has tied up with 11 banks to refinance a $1 billion (Rs.4,930 crore) loan taken to fund the purchase of Novelis Inc. Deutsche Bank AG and three Japanese banks will be among the lenders to Hindalco. Net profit rose to Rs.720 crore in the three months ended 30 September 2008.

The status of the company's expansion projects include:

  • The capacity of Muri alumina refinery expansion project from 11,000 tpa to 4,50,000 is mechanically complete. Production is being up in a phased manner. The entire steam and power requirement is being met by the new captive power plant. The production from the expanded facility is slated to reach its full capacity by end 2008.
  • Hirakud Phase II expansion of the smelting capacity from 1,00,000 tpa to 1,43,000 tpa is completed as per schedule. Further work on expansion to 151 ktpa is in progress and is expected to be completed bby August 2009, whereas the power generation capacity  has been raised from 267.5 MW to 367.5 MW.
  • The allotment of the lease of bauxite mines for expanding the alumina refinery capacity from 3,50,000 tpa to 6,50,000 tpa at Belgaum in Karnataka.
  • Aditya Aluminium, the integrated aluminium project having 1 to 1.5 million tpa alumina refinery, 2,60,000 tpa to 3,59,000 tpa aluminium smelter and 750 to 900 MW capacity power plant is as per schedule. A major portion of the total land required for the project has been acquired. MoEF clearance have been obtained for the smelter, the power plant and the alumina refinery. The first metal from the smelter is scheduled to be produced by October 2011 and the refinery is due to be mechanically completed by January 2013.
  • The Mahan aluminium project with a smelter capacity of 3,59,000 tpa and captive power plant of 900 MW is on track. The land acquisition for the project is underway. The company has been allotted a coal block in a JV with the Essar Group for the coal requirement of the CPP. Preliminary environmental clearance have been obtained. The production of coal is expected to start by October 2009. The basic engineering activities for the smelter is expected by July 2011.
  • The smelter capacity of the Jharkhand aluminium project is 3,59,000 tpa and a captive power plant of 900 MW. The plant location is being shifted from Latehar to Sonahatu block. The technology contract for the smelter has already been executed with Alumiium Pechiney.
  • The construction of Utkal alumina refinery with a proposed capacity of 1.5 million tpa is currently underway. The company has acquired the land for the plant and other facilities. The basic engineering packages have already been received from Alcan, while the detailed engineering for the main plant area is nearing completion. The mechanical completion of the plant is slated for Jnauary 2011 and the first alumina is expected to be produced arounf July 2011.
  • Hindalco Almex Aerospace, a JV company for the manufacture of high strength aluminium alloys for applications in the aerospace, sporting goods and surface transport industries is at the advanced stage of implementation. The project is expected to be completed shortly.