Here is a brief status report of various projects of Hindalco Industries, as per a company press release.

Muri, Jharkhand: The brownfield expansion from 110,000 TPA to 450,000 TPA, at Muri Alumina Refinery is in its final stages of completion, and is expected to be commissioned by the first quarter of next fiscal. (Note: the Muri refinery was earlier part of Indian Aluminium Co which was later merged with Hindalco Industries) (project details)

Hirakud, Orissa: The commissioning of Phase I (65,000 tpa to 100,000 tpa) of the expansion of aluminium capacity at Hirakud in Orissa has begun before time. Ten pots were energized on 28 September 2006, and the ramp up is underway. A total of 150 pots will be commissioned by December 2006, ahead of schedule. Phase II of the project, which entails raising capacity from 1 lakh tpa to 1.43 lakh tpa is moving smoothly and is slated for commissioning on schedule. (project details)

Belgaum, Karnataka: For the expansion of alumina refining capacity at Belgaum, Karnataka from 3.5 lakh tpa to 6.5 lakh tpa, the company is awaiting bauxite mining lease. (project details)

Utkal, Orissa: Work at the site of the 1.5 million tpa greenfield alumina refinery project in Orissa is on track. Preparation of pile foundation and plant infrastructure is on track. Land acquisition is complete and detailed engineering has commenced. (project details)

Aditya Aluminium, Orissa: The greenfield integrated 1.5 million tpa alumina refining and 325,000 tpa aluminium smelting project in Orissa is on course. The project has received approval for SEZ status for the smelter. The bauxite mining plan has been approved by the Indian Bureau of Mines, Bhubaneswar. Land acquisition and the rehabilitation and resettlement packages are progressing well. (project details)

Bargawan, Madhya Pradesh: The Company has signed an MoU with the Government of Madhya Pradesh, for setting up a 325,000 tpa Aluminium smelter and a 750 MW Power Plant at Bargawan, Sidhi District, Madhya Pradesh. This project has been granted SEZ status as well.

Mahan Coal block has been allotted to the Essar-Hindalco JV entity– Mahan Coal Company Ltd. The key management personnel are being located here. Permissions have been obtained for additional drilling for assessment of coal reserves and the formulation of a mine plan. The Topographical Survey for contour mapping, identification of villages, number of houses and households, roads, mapping of land records etc has begun.

The Topographical Survey has been completed for Smelter. Applications for acquisition of appx. 5,000 acres of land shall be filed by next month. The project has received concurrence approval for sourcing 45 Cusecs of water p.a. from the nearby Gopad River. (project details)

Jharkhand: The Company had signed an MoU in 2005 with the Government of Jharkhand for a 325,000 TPA aluminium smelter and a 750 MW power plant. The Company is awaiting allotment of a coal block in line with the terms of the MoU.

Selection of land has been finalized. An application for the acquisition of 5,322 acres of land was submitted to JIIDCO in July 2006. Applications for water, construction power and other necessary infrastructure are being put up. (project details)