Hindalco completes Dahej copper smelter expansionIllustrative image – not actual.

Hindalco Industries has completed the expansion of its Dahej copper smelter in Bharuch district of Gujarat. Commercial trials are currently underway.

The expansion has resulted in the copper smelter's capacity rising to 5 lakh tpa from the earlier 2.5 lakh tpa, making Hindalco Industries the largest copper producer in the country.

The expansion plan, costing around Rs.1,200 crore, was launched in April 2004 and was commissioned four months ahead of schedule. The Dahej copper smelter began operations in 1999 with a capacity of 1 lakh tpa, which was expanded to 2.5 lakh tpa in two phases. The preceding expansion that raised capacity from 1.8 lakh tpa to 2.5 lakh tpa was completed  in September 2003, much ahead of the targeted date of March 2004.

Hindalco would be sourcing copper concentrates largely from Mt Gordon and Mt Nifty copper mines in Australia, which were acquired in 2003.

Earlier during April 2005, Sterlite Industries received government nod to start production at its recently-expanded Tuticorin smelter in Tamil Nadu. The project to expand smelter capacity from 1.8 lakh tpa to 3 lakh tpa had achieved mechanical completion in January 2005.

With both these projects commissioned, India's copper producing capacity would rise to nearly 9 lakh tpa.

Hindalco Industries is on a major expansion drive. It recently announced its plans of setting up a greenfield 2.6 lakh tpa integrated aluminium smelter in Orissa costing Rs.11,000 crore and another with capacity 3.25 lakh tpa in Jharkhand. It may be recalled that in late March 2005, Hindalco Industries raised rupee loans of Rs.5,500 crore -- the largest domestic syndicated loan -- in Indian corporate sector.