Illustrative image – not actual.The Himachal Pradesh government has asked Jaypee Karacham Hydropower to relocate its transmission lines in the state to avoid felling of trees.
Jaypee is setting up a 1,000 MW project in Kinnaur district. The company has been told to lay the transmission lines on the right bank of the Sutlej river instead of the left bank. The right bank does not have any forest cover or major habitation. Therefore, more than 22,000 trees situated on the left bank will be saved.
The government has also rejected the application of Allain-Duhangan Hydro, another hydropower firm, to clear forest land to set up a 192 MW project in the Kullu district. All power companies located in same river basin have been asked to use only one power corridor, for the distribution of power.