High speed rail corridor construction work to start in 2017Illustrative image – not actual.

The Indian Railways plans to start the construction work of the high speed train between Mumbai and Ahmedabad in 2017.

It will take about seven years after the awarding of the contract for the project to be completed as a lot of new technologies will be used to construct the high-speed corridor.

The Special Purpose Vehicle (SPV) National High Speed Rail Corporation formed to implement the Mumbai-Ahmedabad high speed bullet train project, is meeting on 20 April 2016 to finalise the technical details including standardization process for construction of tunneling, pillars, fencing and other requirements of the mega project.

The bullet train is expected to cover 508 km between Mumbai and Ahmedabad in about two hours, running at a maximum speed of 350 kmph and operating speed of 320 kmph.

Estimated to cost about Rs 97,636 crore, 81 per cent of the funding for the project will come by way of a loan from Japan.
 