Illustrative image – not actual.The scope of work envisages construction of eight-lane carriageway starting near junction with NH-11 A to Junction with MDR-1 (Baonli-Jhalai road) (ch 214.260 - 247.310) section of Delhi-Vadodara green field alignment (NH- 148N). The work will entail an investment of Rs 880.11 crore with completion period of two years.The length of the road project is 33.05 km.
The scope of work also envisages construction of eight-lane carriageway starting near Junction with MDR-1 (Baonli-Jhalai road) to end of interchange on NH-552 (Tonk-Sawai Madhopur) near village Mui (ch 247.310- 292.950) section of Delhi-Vadodara Access Controlled Greenfield Alignment (NH-148). The work will cost Rs 1,258.11 crore to be completed in two years. The length of the road project is 45.64 km.