Launched in 2016, the project is facing delays. During a recent visit to the project site by the field research team of Projects Today, it was learnt that around 96 percent of work on the project has been completed and the health centre will be opened for public in July 2018. The hospital was to be completed in January 2017 as per the original schedule.
A building of G+one floor with various modern amenities is designed by Sopan Prabhu Architect and Planner. Moksh Constructions is the contractor and project management consultancy (PMC) service is offered by Adharshila Consultants.