Hindustan Copper (HCL) has submitted its DPR to Investment Promotion Board for proposed Rs 2,500-crore mining project at Malanjkhand, in Madhya Pradesh.
HCL has requested for the Board's approval in the DPR, along with elaboration on the various business models. It has preferred a turnkey contract route for development and construction of underground mine, below the existing open cast mine as also a separate contract for mine operation according to the already prepared mine plan. This model is likely to give HCL best returns from the project among all others.
This model involves milestone payments to the turnkey contractor, which will be selected through a global bidding process. This means that the mine construction cost is borne by HCL.
The other applicable models include the one that place cost burden on the contractor, who also bears the risk. In this case, HCL's return from the project will be much lower than the turnkey contract model. The third hybrid model involves a service contract where ore/metal-in-concentrate is supplied on pre-fixed per unit basis. The cost of construction here also is largely borne by the contractor. The last model prescribes HCL to take up the construction and mining project on its own.
In 1991-92, BC Metal of Japan prepared a technical report for the project. The present DPR has been prepared in-house, by HCL, with broad technical references to the BC Metal's report.