Hindustan Construction Company (HCC) and Vensar Constructions Company (VCCL) joint venture has bagged a contract worth Rs 489 crore from Delhi Metro Rail Corporation (DMRC) under Phase-IV of the Delhi Metro project.

The share of HCC in the JV is 75 percent i.e. Rs 367 crore. The contract is for design and construction of 2.03 km long twin tunnels on Janakpuri West to R K Ashram corridor (Extension of Line 8) of Phase-IV.

The twin tunnels will be constructed using Shield Tunnel Boring Machines. The contract also includes construction of an underground station, namely Krishna Park Extension.

The work is expected to be completed in three years period.

HCC has completed 1.54 km long CC66 package of DMRC on Dwarka-Najafgarh Corridor in October 2019. This was the sixth DMRC contract successfully completed by the company.

 