Illustrative image – not actual.
The Hindustan Construction Company- KEC International (HCC-KEC) JV emerged as the lowest (L1) bidder for the construction work of Chennai Metro Phase-2 Line-5.
The consortium emerged as L1 bidder for 11.61 km Puzhuthivakkam- Sholinganallur section (Package C5-ECV-03) which consists of 11 stations at the extreme southern end of Line-5 (Madhavaram-Sholinganallur).
Chennai Metro Rail (CMRL) invited bids for this package’s construction in November 2020 with an undisclosed estimate and 36 month deadline. Technical bids were opened in June-end 2021 to reveal three bidders.
The scope of work envisages construction of elevated viaduct of approximately 11.61 km length from Ch 33,710 mtr to 45,320 mtr between Puzhuthivakkam Metro station (excluding) and beyond Elcot Metro station including construction of 11 nos of elevated stations at Madipakkam, Kilkattalai, Echangadu, Kovilambakkam, Vellakkal, Medavakkam Koot Road, Kamaraj Garden Street, Medavakkam Junction, Perumbakkam, Global Hospital and Elcot and all associated works in Corridor-5 of Chennai Metro Rail Project- Phase-2.