Illustrative image – not actual.HCC Concessions (HCON), the infrastructure development arm of HCC Group, concluded its conciliation with the National Highways Authority of India (NHAI) for all disputes concerning Baharampore-Farakka Highways (BFHL) and Farakka-Raiganj Highways (FRHL).
The SPVs entered into settlement agreements with NHAI for a comprehensive closure of all outstanding disputes and claims between the parties.
BFHL will receive Rs 405 crore while FRHL will receive Rs 854 crore from NHAI. FRHL will release the settlement proceeds and further sums to HCC Group as per the existing contractual understanding with FRHL's buyer, Cube Highways & Infrastructure II Pte (Cube).
Besides part use of funds for NHAl project completion and an exit to the Xander Group, who hold 14.55 percent share in HCON, a substantial portion of funds will be received by HCC as a settlement of their cost claim.
Farakka Raiganj Highways (FRHL) as a further consequence of this conciliation, Cube will release Rs 233 crore withheld as part of HCON's sale of FRHL and also require to share a significant portion of FRHL's growing revenue for the remainder of the concession's 20 years.
With 100 percent construction completion being achieved at FRHL, toll rates will increase 70 percent in FY22. Additionally, up to Rs 100 crore is further payable by Cube in 2023, contingent on traffic projections being realised.
BFHL's closure of disputes with NHAl facilitates the required liquidity in the project to accelerate completion of a much-delayed Bypass, which along with the SPV's strong free cash flow from toll operations, frees HCON to monetise this Rs 2,000 cr mega project earlier than planned.
The SPVs entered into settlement agreements with NHAI for a comprehensive closure of all outstanding disputes and claims between the parties.
BFHL will receive Rs 405 crore while FRHL will receive Rs 854 crore from NHAI. FRHL will release the settlement proceeds and further sums to HCC Group as per the existing contractual understanding with FRHL's buyer, Cube Highways & Infrastructure II Pte (Cube).
Besides part use of funds for NHAl project completion and an exit to the Xander Group, who hold 14.55 percent share in HCON, a substantial portion of funds will be received by HCC as a settlement of their cost claim.
Farakka Raiganj Highways (FRHL) as a further consequence of this conciliation, Cube will release Rs 233 crore withheld as part of HCON's sale of FRHL and also require to share a significant portion of FRHL's growing revenue for the remainder of the concession's 20 years.
With 100 percent construction completion being achieved at FRHL, toll rates will increase 70 percent in FY22. Additionally, up to Rs 100 crore is further payable by Cube in 2023, contingent on traffic projections being realised.
BFHL's closure of disputes with NHAl facilitates the required liquidity in the project to accelerate completion of a much-delayed Bypass, which along with the SPV's strong free cash flow from toll operations, frees HCON to monetise this Rs 2,000 cr mega project earlier than planned.