HCC completes 3.82 km tunnel for Mumbai Metro 3Illustrative image – not actual.

The Hindustan Construction Company (HCC) has completed boring the first 3.82 km long tunnel of Mumbai Metro 3. HCC has finished the south-bound tunnel between Chhatrapati Shivaji Maharaj Terminus (CSMT) and Mumbai Central stations, becoming the first contractor among all others to complete the entire length of a tunnel for the Metro 3 project.

HCC maintained an average drilling rate of around 8.20 mtr per day for the 3.82 km long tunnel passing via the station boxes of Kalbadevi, Girgaon and Grant Road. This section is part of the 33.50 km long Metro 3 line connecting Colaba-Bandra-SEEPZ (Andheri East) and will be the first fully underground Metro in the city.

It is being built at a cost of around Rs 23,136 crore, with Rs 13,325 crore loan from the Japan International Cooperation Agency (JICA). The Mumbai Metro Rail Corporation (MMRCL) had awarded the contract to HCC in July 2016 for design and construction of twin tunnels by Tunnel Boring Machines (TBM) and construction of four underground Metro stations at CSMT, Kalbadevi, Girgaon and Grant Road.

With the tunneling work completed well within the stipulated time, HCC has now taken up the work of constructing underground Metro stations, each with a unique design.

← All latest storiesBack to top →