Hindustan Construction (HCC) has been awarded a Rs 635 crore contract by NTPC to construct head race tunnel for Tapovan Vishnugad hydro-electric power project on river Dhauliganga in the Chamoli district of Uttarakhand.
This is an item rate contract involving salvaging of Double Shield Tunnel Boring Machine (TBM) stuck in the earlier operation by other contractor, refurbishing and putting it in operation to construct a 2.84 km long head race tunnel and installation of segmental lining. The contract also involves construction of 1.66 km long tunnel using drill and blast method and concrete lining.
The project is scheduled to be completed within 34 months.