The High Court, accepting the writ petition filed by a consortium -- Trishe Energy Infrastructure Services and Central Southern China Electric Power Design Institute - remitted the matter back to Tangedco to reconsider the bids of BHEL and the consortium strictly in accordance with law and Tamil Nadu Transparency in Tenders, 1998.
The consortium and BHEL were the key bidders [to bag contract] for the Rs 9,207 crore project to build two power plants of 660 MW each at Ennore SEZ.
The consortium moved the high court saying that BHEL should have been disqualified from the bidding process, as it had delayed earlier power projects involving a cumulative value of Rs 27,000 crore and 7,300 MW in Tamil Nadu.