Illustrative image – not actual.The Hazira-Dahej-Hazira gas pipeline, built by Dodsal for Indian Petrochemicals Corporation, has been dedicated to the nation, ahead of schedule.
Dodsal has developed the pipeline on
build-own-operate-transfer basis. The company was involved in the project right
from the concept to the commissioning stage, including acquisition of right of
way, all statutory approvals and engineering, procurement and construction.
The project was implemented in 10 months from financial
closure. The pipeline built at a cost of Rs.354 crore is capable of
transporting 11 million standard cubic metres per day of natural gas over a
distance of 196 kms from Hazira to Dahej and back.
Dodsal had also organised debt funding from
Infrastructure Development Finance Corporation, Industrial Development Bank of
India and Life Insurance Corporation of India for the project.