Hassan-Chikkanayakanahalli to be operational soonIllustrative image – not actual.

Hassan-Chikkanayakanahalli road project in Karnataka is expected to be operational soon.

 

The 74 km Hassan-Chikkanayakanahalli stretch (SH-71) is being developed by the Karnataka Road Development Corporation (KRDCL), with an estimated cost of Rs 241 crore. Abhijit Construction Company, contractor of the project, commenced work on the project in January 2012, and it is scheduled to be completed by January 2014.

 

The work however, was kept on hold for a year, due to legal issues. Meanwhile, as per the court order, the company resumed work from end August 2013, and expects to complete the work in a couple of weeks.

 