Illustrative image – not actual.Construction work on the Hassan-Bengaluru new railway line is moving at a snail’s pace in Karnataka.
The project has not been able to make significant progress due to unavailability of land.
The South Western Railway (SWR) claims that about 150 ha is yet to be handed over for the new line between Shravanabelagola and Nelamangala while the state government says all land on this 110-km stretch has been handed over to the SWR and only 25 acre needs to be transferred to the SWR for the purpose. Also, the state government had decided to share half of the project cost with the SWR besides offering land free of cost with effect from 1 April 2010. The total length of the rail line is 172 km.
The project was sanctioned in 1996. So far, work on 42-km stretch between Hassan and Shravanabelagola has been completed.