Rai Bahadur Narain Singh Sugar Mills' 1,900 tccpd sugar unit in Krishnagiri district of Tamil Nadu is nearing completion.

Rai Bahadur Narain Singh Sugar Mills' 1,900 tccpd sugar unit in Krishnagiri district of Tamil Nadu is nearing completion. With 90 per cent work already complete, the Rs.47 crore project is scheduled to commission by end-February 2007.

The project also involves setting up of a 30 MW cogeneration power unit. One unit of 14 MW is already complete and the entire power plant is slated to commission by October 2007.