Hanuman Alloys to expand Bokaro steel unit Illustrative image – not actual.

Hanuman Alloys is planning to expand its steel unit at Bokaro Industrial Area, in Bokaro district of Jharkhand.


The expansion project is estimated to cost Rs 30 crore. Around 75 per cent of the project cost will be funded through bank loan and the remaining 25 per cent from internal accruals.


The project will spread over eight acre of land and will include the following products:

 

Products

Capacity (From) In tonne per annum

Capacity (To) In tonne per annum

Induction Furnace

15,000

33,000

Rolling Mill

30,000

36,000

Ferro Alloys

-

45,000

Slag Crushing

-

  1,500

 

As told to ProjectsToday, the machinery supplier is yet to be finalised and the company is also awaiting environmental clearance for the project.


Hanuman Alloys has appointed Mr Deepak Singh from Bokaro as the civil contractor for the project.


Work on the steel project is expected to commence by February 2015.

 

More Project Info:
Steel (Bokaro) project - Expansion

← All latest storiesBack to top →