Illustrative image – not actual.
H G Infra Engineering has received provisional completion certificate by the authority engineer of Redecon India in association with Jaiman CC vide letter dated 10 June 2020.
The project involved upgradation of two-lane with paved shoulder for section from 58.00 km to 91.600 km excluding chainage (59.460 to 62.900), (73.120 to 75.920), (82.650 to 85.300) Balotra to Sanderao via Jalore section of NH-325 (Package-II) on EPC mode in Rajasthan.
The cost of the project is Rs 113.31 crore. The appointed date for the project was 20 July 2017.