H G Rewari Ateli Highway, a wholly-owned subsidiary of H G Infra Engineering, has received provisional completion certificate for the road project in the state of Haryana.
The provisional certificate of completion dated 31 December 2021 has been issued by the authority and the project has been provisionally declared fit for entry into operation on 15 November 2021.
The scope of project involves upgradation of four lane of Rewari-Ateli Mandi (Package-III) section of NH-11 from 11.780 km at Rewari to Ex 43.445 km near Ateli Mandi (design length 30.45 km) as Feeder Route in Haryana on hybrid annuity mode (HAM).
The bid project cost by the company is Rs 580 crore. The construction period of the project is for two years, with operation period of 15 years.