H G Infra Engineering has been declared the lowest (L1) bidder by Ircon International for a new BG electrified double railway line for Chhattisgarh East West Rail Corridor.
The scope includes civil works including earthwork for railway formation, blanketing work, minor bridges, major bridges, ROBs, RUBs, FOBs, track linking works (including supply of ballast but excluding supply of rails and sleepers), station building and other service buildings, staff quarters, platform works including general electrical works between Gevra Road (0 km) to Sendurgarh (67 km) double line and Urga (0 km) to Kusmunda (11.51 km) single line in connection with construction of the new BG electrified double railway line for Chhattisgarh East West Rail Corridor from Gevra Road (0 km) to Pendra Road (135 km) via Dipka, Kathghora, Sendurgarh and Pasan in the state of Chhattisgarh over the South East Central Railway.
The bid price placed by H G Infra Engineering is Rs 784.99 crore. The completion period for the project is 30 months.