GVK seeks approval to use HSD for gas-based power project Illustrative image – not actual.

GVK company has sought approval from the Ministry of Environment & Forests (MoEF) to use high speed diesel (HSD) instead of natural gas at its plant in East Godavari district of Andhra Pradesh.

 

As gas supplies for the project have come down due to a reduction in gas production in the KG D6 fields, it is requested to amend the environment clearance for using HSD (green diesel) with sulphur content not exceeding 0.05 per cent as an alternate fuel instead of emergency fuel. The project is being executed by Gautami Power.

Since October 2011, the total gas supply from KG D6 has been reducing from the original level and supply to the power sector has been stopped since March 2013.

 

However, the Expert Appraisal Committee (EAC) under the MoEF opined that the quantity of HSD to be utilised for power generation is quite substantial, which will not be as eco-friendly as natural gas. The Committee, therefore, desired that the company should obtain the views/comments of the Ministry of Power and Ministry of Petroleum & Natural Gas on the proposal, before taking a decision.

 

The project has natural gas allocation of 1.96 million standard cub mtr per day by Ministry of Petroleum & Natural Gas from KG Basin for operating the plant at full capacity. The plant operated on full generation during 2009, 2010 and 2011 using gas supplied from KG D6 gas fields.

 