Illustrative image – not actual.GVK Power has inked a Rs.3,000 crore long term agreement on 11 December 2008, with the Indian Railways for the transportation of coal for its upcoming 2X300 MW thermal power plant at Goindwal Sahib in Punjab.
The agreement assures the supply of coal to the power plant for a period of 25 years and provides for premium charges and penalty charges for both the parties. The Indian Railways will supply 52-55 rakes for transporting 2.528 million tpa of coal from GVK's coal fields located at south Karanpura in Jharkhand.
GVK will be paying an additional five per cent of the freight charges on each tonne of coal loaded up to annual scheduled quantity of 2.52 million tonne. Also, the company will pay a bonus of five per cent of the freight charges on the additional quantity actually transported over and above 95 per cent of annual scheduled quantity. Railways will supply BOXN wagons for handling this traffic.
For this power project, the company has already borrowed Rs.30 billion from banks and the lender for this project is IDBI Bank.
Ministry of Railways had already entered into similar agreements with Rosa Power Supply Co Ltd and Nagarjuna Power supply Co Ltd in 2007.
Related Links:
Project profile