GUVNL invites tenders for long-term PPA'sIllustrative image – not actual.

Gujarat Urja Vikas Nigam Limited (GUVNL) has invited tenders from power suppliers to provide 3,000 MW in the range of 2,400 to 3,600 MW power.

GUVNL has stated that the bidders are free to choose any technology through gas turbines, diesel generator sets, conventional coal or lignite fired boiler or hydro plant for generating power.

The bidders shall have to commence power supply to the state grid within 48 months from the signing of the PPA. The bidders can submit their response for a minimum capacity of 100 MW. The term of PPA set to 25 years in case of supply of power from thermal generation source and 35 years in case of supply from hydro-electric generation source.