Guru Hargobind power plant: Unit III & IV to go commercial by OctoberIllustrative image – not actual.

The Unit 3 & 4 (250 MW each) of Guru Hargobind power plant (Stage II), also known as Lehra Mohabbat power project near Bhatinda will go fully commercial by end-October 2008, nearly 15 months behind schedule.

The project is delayed because of poor regulations and procedures by Bharat Heavy Electricals, the EPC contractor of the project, which in turn has resulted in substantial power shortages. BHEL is likely to pay Punjab State Electricity Board a penalty of up to five per cent of the total cost of the project.

Other projects where BHEL is the EPC contractor have also been delayed like Amarkantak (MP), Chandrapura (Jharkhand) and Bellary (Karnataka).