Illustrative image – not actual.The new Metro corridor connecting Millennium City Centre with Cyber City in Gurugram is facing delays which could make its 2029 completion target difficult to achieve.
The project is being developed in two phases. Phase-I, covering 15.3 km between Millennium City Centre and Sector 9, is already under construction after the contract was awarded in August 2025. However, Phase-II has yet to enter the construction stage because its civil construction tender has not been invited. Construction is expected to require around two-and-a-half years, followed by testing and commissioning.
Phase-II involves tendering to commissioning, leaving limited time to meet the overall 2029 target.