Gurgaon-Jaipur NH project by June 2016Illustrative image – not actual.

The construction of six-laning of Gurgaon-Jaipur National Highway project which started on 03 April 2009 is likely to be completed by 30 June 2016.

As per the original schedule, the project was to be completed by September 2011. The main reasons for delay in completion was due to delay in land acquisition caused by delay in disbursement of compensation by competent authority of land acquisition, delay in removal of government structures and religious structures.

Other reasons are delay in shifting of high tension lines, electrical utilities and water supply utilities and delay in handing over of forest & irrigation land by Haryana Government.