Gulf Petrochem commissions Phase-I of liquid storage terminalIllustrative image – not actual.
Gulf Petrochem has commissioned Phase-I of its liquid storage terminal at Pipavav port in Gujarat.

 

Phase-I has a capacity of 1,10,000 KL. Phase-II, which will be commissioned by mid-March 2015, will have a capacity of 1,40,000 KL.

 

The terminal has a total of 46 tanks of different capacities which befits different product requirements for all classes of petroleum products, chemicals, petro chemicals, vegetable oil, lube base oil, fuel oil and also bitumen.

 

It also has an exclusive oil berth with a draft of 12 mtr for handling medium range vessels that carry up to 40,000 tonne of cargo.

 