Gujarat wind power developers get respite to do financial closure of projectsIllustrative image – not actual.
The wind power developers in Gujarat have got two months’ time from the Solar Energy Corporation of India (SECI) to do financial closure of their proposed projects. The decision comes as a relief for projects with a capacity of 1,700 MW that were facing a penalty of Rs 10,000 per MW per day for delays in financial closure.

The Central government had stepped in to solve the dispute between wind power project developers and the Gujarat government. The projects under pressure have been won by Inox Wind, Mytrah Energy, ReNew Power, Alfanar Sprng Energy, Green Infra Wind Energy, BPL Energy and Torrent Power.

Project developers attributed the delay to the hurdles in getting land for lease for wind projects auctioned by Central agencies such as SECI. The state government also demanded from developers assured supply of power to the state power distribution company (Discom) in return for allocation of land for the projects.