The Gujarat
Infrastructure Agenda - Vision 2010 had targeted to achieve power
generation capacity of 17,000 MW by the year 2010. This was proposed to be
achieved with an investment of Rs.56,283 crore. However, the target is likely
to be scaled down by 20 per cent for want of adequate funds.
Of the total investment required,
the State government contribution was to be a meagre Rs.3,200 crore, while the
private sector was expected to bring in Rs.53,083 crore. Investment in
generation was expected to be Rs.33,770 crore, while that in transmission -- Rs.22,514
crore.
It may be mentioned that in its 1995 Power Policy, the State government had set a target of achieving generation capacity of 15,000 MW by the year 2000. However, the actual capacity in the State is only around 8,500 MW, at present.