Gujarat Pipavav drops plan for crude oil jettiesIllustrative image – not actual.

Gujarat Pipavav Port Ltd (GPPL) has shelved its plan to set up jetties for handling crude oil. The company will instead focus on setting up facilities for handling container and other cargo.

 

GPPL had earlier floated tenders for the construction of two 300-metre long dedicated, full-fledged, shore-based jetties. Work on these jetties was expected to be completed within 18 months. GPPL had identified Shiyalbet Island, located 1.5 km off the main port at Pipavav, for setting up the terminals. Around 36 acres of land had been reserved for the purpose. The Gujarat Pollution Control Board, the state environment department and the Union Ministry of Environment & Forests had issued no-objection certificates to GPPL for handling liquid cargo.

 

L&T, Afcons, Trafalgar House and Simplex had responded to GPPL’s tender.