The Gujarat government has cancelled a resolution from 2018 that allowed Tata Power, Adani Power and Essar Power to increase tariffs after coal prices declined since then.

The three power generation companies operate projects that run on imported fuel and had sought the increase in tariffs to account for higher coal prices.

However, in an order in April 2020 related to Essar Power, the Gujarat Electricity Regulatory Commission (GERC) made some modifications as coal prices had softened, which the state government now wants to incorporate in power purchase agreements (PPAs).

The government resolution from 2018 has been revoked as the coal market has changed.

GERC had given directions that aim to allow prudent cost of coal as a pass-through so that if private generators are facing any hardships, that is reduced but at the same time the customers’ interest is taken care of. The government would examine future PPAs on the back of these directions.

The main objective of the above directive was to protect interests of consumers while ensuring supply of power from 4,805 MW capacity at reasonable rates.

Further, in view of market trend of Indonesian coal price, changed scenario and to safeguard interest of consumers, the government of Gujarat has revoked the GR as the same was not fulfilling its objective and purpose.

In an order dated 12 June 2020, the state energy ministry notified that while the earlier resolution is revoked, supplemental PPAs with Tata Power arm Coastal Gujarat Power (CGPL) and Essar Power will be signed to factor in  GERC’s directions.

In the case of Adani Power, GUVNL filed a recall petition seeking cancellation of relief allowed earlier, which was pending with the Central Electricity Regulatory Commission (CERC). Until CERC gives an order, GUVNL will consider energy charges for Adani Power on a provisional basis.

The Gujarat government has also directed GUVNL to file a separate draft PPA for CGPL, incorporating GERC’s directions, for approval.