Illustrative image – not actual.Gujarat Electricity Board (GEB) has stalled purchases from the Hong Kong-based CLP Power International's 655 MW Paguthan power project since October 2001 as the cost of the naphtha-based power being produced by the plant is substantially higher than that produced by other independent power producers, viz. Gujarat Industries Power Corporation (GIPCL) and Essar Power.
According
to GEB, the cost of power supplied by GIPCL and Essar Power is around Rs.2.50
per unit and that of CLP’s is around Rs.3.50 per unit. GEB is willing to cough
up fixed charges, of around Rs.80-90 crore, under the power purchase agreement
signed with Paguthan plant, rather than buy the expensive power.
According
to reports, GEB is not paying even the charges and its dues amount to around
Rs.300 crore. These dues are being written off by CLP against the sale of
Gujarat Power Corporation’s 12 per cent stake in the Paguthan project to CLP.
CLP
has thus recently applied for excise duty waiver in a bid to make its power
more competitive in the market.
It
may be recalled that the Enron-promoted Dabhol Power too faced a similar fate,
when MSEB expressed its inability to buy power from DPC as it proved expensive.
