Illustrative image – not actual.Gujarat State Petronet Ltd (GSPL) plans to speed up its Rs.3,000 crore gas grid project with an investment of Rs.125 crore in the next seven months.
The gas grid project envisages laying 1,126 kms of
LNG pipelines in two phases in the State.
The first phase would entail an investment of
Rs.1,400 crore for laying 525 kms of pipelines from the Gujarat-Maharashtra
border to Vadnagar, via Baroda and Ahmedabad. This phase is scheduled for
completion by 2003.
Work on this phase has already started and the
pipeline between Hazira and Mora has already been commissioned. The company has
also awarded Aban Constructions the contract to lay a 45 km pipeline from
Ankleshwar to Dahej. Further, the contract for making a passageway across the
Narmada river near Bhadbhut, 16 kms from Amboli has been awarded to PNL-Nacap,
a joint venture between PNL and Nacap, Malaysia.
The second phase is estimated to cost Rs.1,600 crore for laying 523 kms of pipelines covering mainly the Saurashtra region.