The Gujarat State Petroleum Corporation (GSPC) is expected to begin commercial production of gas from its DD-West field in the Krishna-Godavari basin off the Andhra Pradesh coast from December 2011.

The Director General of Hydrocarbon (DGH) has already certified two trillion cubic feet of natural gas from GSPC's DD-West field.

The GSPC has worked out a detailed Field Development Plan (FDP), under which gas production of 200 million standard cubic feet per day (mmscfd) from the DD-West field has been envisaged for a plateau period of 12 years.

The facilities being set up will initially have a capacity to handle 400 mmscfd of gas, and full development of the gas field is likely to have a peak production of 600 mmscfd for a plateau of 10 to 12 years. It is also envisaged to set up a six-legged 16-slots well, head platform connected to a process platform through a bridge, 24 km-long sub-sea pipeline and onshore gas terminal at an estimated cost of $1.8 billion (approx Rs 8,640 crore).

GSPC will have a technological tie-up with some foreign companies for deep-sea drilling for the commercial production of gas. It is already in talks with Reliance to use its pipeline for routing the KG basin gas from Kakinada (Andhra Pradesh) to Gujarat.

Also See:

DGH nod to GSPC's development plan for KG basin (21-Sep-09)

 

← All latest storiesBack to top →