GSPC raises capacity of LNG unitIllustrative image – not actual.

Gujarat State Petroleum Corporation (GSPC) has raised the capacity of its planned LNG terminal by 30 percent from 5 to 6.5 million tpa after a fall in prices of metals used in construction.

GSPC aims to have the plant ready by 2013 at a cost of Rs.3,000-3,500 crore ($630-740 million) and sharp falls in prices of steel and nickel have allowed it to think bigger.

GSPC will hold a 50 per cent stake in the project, while India's Adani group will take 25 percent. The remaining 25 per cent will be sold to financial institutions or state refiners.

Also See:

GSPC shortlist consultant for Mundra LNG project (10-Oct-08)