Gujarat State Petroleum Company in collaboration with Niko Resources has decided to begin offshore gas production by 2004 from its field at Hazira. Four acres of land is yet to be acquired for the development of the offshore project. The consortium has been producing gas from 20 onshore wells in Hazira near Surat since July 1995

 

A recent evaluation by the company has revealed that offshore gas production will increase its total output by 40 per cent to about 5.6 million cubic metres per day. Since their production in 1995, the fields have been producing 4 cubic million metres per day. The offshore facilities would be developed by February 2004 and the production would commence from April 2005.

 

The consortium has obtained a no-objection certificate from Gujarat Pollution Control Board while clearance from Ministry of Environment and Forests is awaited.

 