GSPC, Niko Resources plan offshore platform at HaziraIllustrative image – not actual.

Gujarat State Petroleum Corporation and Niko Resources of Canada, have plans to set up an offshore platform at Hazira with an investment of Rs.300 crore.

 

This decision follows a meeting among the officials of GSPC, Niko Resources, the Directorate General of Hydrocarbons and international appraisal agency, Degolyer & McNaudhton (D&M).

 

At the meeting it was decided that the Hazira fields have more reserves than that calculated by D&M during the preliminary stage of the investigation, for which a report was submitted in September 2001.

 

The increased reserve base of approximately 6 billion cubic metres over the initial estimate has been calculated using improved technology used for applying inversion methodology resulting into better understanding of sand geometry and its extent over the Hazira structure.

 

However, prior to setting up the offshore platform, GSPC and Niko would drill an appraisal well at the location, estimated to cost Rs.25 crore. Depending on this well, the two companies would take a final decision on proposed the offshore platform.

 

 

Hazira Gas Fields:

 

GSPC and Niko Resources had signed a production sharing contract with the Government of India in 1994. Following this, the Hazira gas fields were taken up for development in 1995. Till date, 19 wells have been drilled resulting in a daily production of over 2 million cubic metres of gas daily.

 

According to the GSPC’s Managing Director, Mr D J Pandian, the proposed exploitation of offshore gas would increase the production of gas, taking the total production to around 4-5 million cubic metres per day. This additional production would cater to the increased demand of the industries in Gujarat, especially to that of the state-owned companies.