Illustrative image – not actual.Gujarat State Petroleum Corporation (GSPC), is likely to get green clearance for laying onshore installations at the KG basin block soon.
The proposed project, which includes pipeline and terminal, is necessary to let the gas flow from the offshore exploration asset. Though the project is under execution, the developer is still awaiting environmental and coastal regulatory zone clearance for laying a 10 km underground pipeline on the peripheries of the Coringa Sanctuary (Andhra Pradesh), and commissioning of the onshore terminal.
Due to delay in getting clearance, the developer has postponed the completion schedule by three months from June 2013. The project, estimated to cost $1.8 billion (approx Rs 10,690.2 crore) will have a peak output of 5.7 to 8.6 million standard cu mtr of natural gas per day.
The GSPC operated consortium (GSPC 80 per cent, Jubilant 10 per cent, GeoGlobal 10 per cent) will initially bring two wells with an estimated production capacity of approximately one lakh standard cu mtr into production. The rest will be brought into production in a phased manner.