Illustrative image – not actual.GSPC on 19 February 2013 invited global bids to select an EPC contractor for LNG re-gasification terminal proposed at Mundra in Gujarat.
The proposed five million tpa terminal will be set up by GSPC LNG (GLL), a JV of GSPC and Adani group The facility will come up with an investment of Rs 4,000 crore. The terminal capacity will be expandable upto 10 million tpa.
In the JV company, GSPC has 50 per cent stake, while Adani group holds 25 per cent and remaining 25 per cent will come from a strategic investor. Currently, GSPC has been scouting for a strategic investor for its LNG project.
The terminal will have two LNG storage tanks. It will have LNG receiving, re-gasification and gas evacuation facilities. Commissioning is expected in first quarter of 2016.
The company has already awarded the front-end engineering and design (FEED) contract to Tractebel of Belgium.
Related Link:
Tender