Corporation plans to start commercial production at its recent gigantic gas
find in the KG basin, by December 2007.
GSPC has pegged initial output at
10 mmscmd, which would increase to 80 mmscmd by 2010. A gas platform for 6 to 9
producing wells would be constructed off the Yanam-Kakinada coast with each
well producing about 1.5 mmscmd of gas.
The development of the field would require an investment of Rs.1,500 crore that would be raised through a mix of internal accruals, debt and equity through the IPO route. GSPC, currently wholly held by Gujarat government, plans to dilute 10-20 per cent of the equity through an IPO in next six to 12 months.
Meanwhile, the Gujarat Chief Minister, Mr Narendra Modi, has stated that the estimated reserves of 20 tcf are “conservative” and that 85 per cent of the estimated reserves can be exploited. The CM was reacting to observations made by the Directorate General of Hydrocarbons that the reserve estimates are “premature”.
GSPC struck 20 tcf of gas reserves in the third well in the block KG-OSN-2001/3, some 6 km from Andhra coast, earlier this week.