GSEC project on schedule; outlines expansionIllustrative image – not actual.

Gujarat State Energy Corporation, which is implementing a 156 MW combined cycle power plant project, has received necessary approvals to augment the capacity of its power plant to 200 MW.

 

The GSEC project is on schedule and it is expected that the first turbine of 52 MW would be commissioned latest by September 2001, the second (52 MW) by October 2001 and the combined cycle by January 2002.

 

The 156 MW natural gas combined cycle power project, costing Rs.576 crore, is coming up at Hazira. The project achieved financial closure in November 2000.

 

The Gujarat Electricity Board has agreed to an escrow cover for the project, which would be limited to the lenders’ liability amounting to around Rs.190 crore.

 

The project would also have two new equity partners, viz. Kribhco with a 25 per cent equity and Gas Authority of India with an 11 per cent stake. The other equity partners in the project are GSPC with other state-owned enterprises who together own 55 per cent of the stake and Steag AG of Germany, the O&M contractor for the project which holds an eight per cent equity.