Green signal to Kopri ROB from CRIllustrative image – not actual.

Widening of the Kopri railway overbridge (ROB) finally received the green signal from the Central Railway. Since 2006, this project had been stalled due to delays by railway authorities over granting the necessary permissions.

 

In 2006, the Public Works Department (PWD) sanctioned the Kopri expansion project which was projected to be completed within two years. The Central Railway approval was a must as the bridge needed to cross over a railway property.

 

The expansion cost has scaled up to Rs 50 crore from the estimated cost of Rs nine crore eight years ago. PWD has revised the designs following changes suggested by the CR. The process of floating tenders will commence soon.

 

Widening work of the narrow Kopri rail overbridge (ROB) on the Eastern Express Highway will help commuters to save at least five to ten minutes of travel time.