Grasim outlines expansion plans for 2001-02Illustrative image – not actual.

Grasim Industries has outlined its expansion plans for the year 2001-02 involving a total outlay of Rs.353 crore. Over the next two years, the company plans to spend Rs.530 crore.

 

The company is planning to set up a grinding unit at Bhatinda in Punjab at a total cost of Rs.83 crore. The plant is expected to go on-stream in the second half of 2001-02.

 

Around 3.3 million tonnes of cement capacity would be added through a change in product mix and debottlenecking. The current capacity of the company is 9.86 million tonnes per annum.

 

Four ready mix cement plants are also being set up at a cost of Rs.33 crore, which are scheduled for completion by September 2001.

 

Two captive power plants with capacities 23 MW and 12.5 MW are expected to be set up at a combined cost of Rs.146 crore.

 

A large part of these expansion costs would be met through internal accruals.