GPPC mulls gas based power plant in GujaratIllustrative image – not actual.

GSPC Pipavav Power Company (GPPC) is setting up a gas based combined cycle power plant project at Pipavav in Gujarat. GPPC is a SPV set up by Gujarat State Petroleum Corporation (GSPC) along with Gujarat Power Corporation (GPCL) to implement a power project to meet energy requirements in Gujarat.

The project to be implemented in phased manner is likely to have two units of 351 MW each under the Phase I. the Unit I is slated to commissioned in December 2010 and the Unit II in March 2011. Under the Phase II, GSPC is likely to add another 351 MW capacity.

The project cost of the Phase-I is estimated at Rs 2,545 crore which is to be funded through 20 per cent of equity and 80 per cent of debt. However, the debt requirement to the extent of Rs 1,935 crore has been tied-up by REC. The equity infusion is likely to be carried out in the ratio 34 per cent, 17 per cent and 49 per cent between GSPC, GPCL and third-party investor, Swan Energy, respectively.

GPPC has appointed BHEL as the EPC contractor through international competitive bidding route and the Notice to Proceed was handed in March 2008.

← All latest storiesBack to top →