Illustrative image – not actual.In Q1 of the current fiscal year, the shipping ministry has spent Rs.57.77 crore through internal and external budgetary resources (IEBR). The following is the project capital expenditure on 12 major ports in 2005-06.
| Government spending on major ports | |||
| (Rs.crore) | |||
| IEBR | GBS | Total | |
| Q1 | 57.77 | 0.00 | 57.77 |
| Q2 | 91.35 | 6.00 | 97.35 |
| Q3 | 153.92 | 56.00 | 209.92 |
| Q4 | 353.67 | 28.00 | 381.67 |
| Total | 656.71 | 90.00 | 746.71 |
The programme would look into enhancing the capacity of ports, particularly on reducing turnaround time in ports. During the first quarter of the current fiscal, the turnaround time in major ports was 3.4 days. The projections say that this time would further come down to 3.38 days, 3.36 days and 3.35 days during the second, third and fourth quarters of the current fiscal. The document says that during 2004-05, the average turnaround time was 3.42 days.
About traffic handled in major ports, the outcome budget says that while during the first quarter of the current fiscal, traffic handled was 100.97 million tonnes. For the subsequent three quarters, the figures would be 100.03 million tonnes, 112.76 million tonnes and 111.24 million tonnes.
For the Sethusamudram Canal project, the document says that it would raise Rs.51 crore and Rs.49 crore during the second and third quarter respectively of the current fiscal, through GBS, while Rs.7 crore would be raised through IEBR during the third quarter.